Traffic Impacts | King Ave. Paving Work Nov 2025 - August 2026
On Clay Kaserne, construction work will take place in the King Ave. area over four phases of work, Nov. 24, 2025 - August 2026.
Be prepared for potential single-lane closures throughout the area and use caution while navigating these work zones.
- Phase 1: Heerstrasse in front of Bldg. 1201 + Lucas Street around Bldg. 1226; Nov. 24, 2025 – Jan. 30, 2026
- Phase 2: King Ave West Side in front of Bldg. 1201 + Bldg. 1215; Feb. 2 – March 27, 2026
- Phase 3: King Ave in front of Bldg. 1202; March 30 – July 3, 2026
- Phase 4: Wurgel Street Bldg. 1202 + 1217; July 6 – Aug. 14, 2026
Click on image to enlarge
Aummanstrasse Closure Traffic Plan Overview | Oct. 6 - Dec. 1 2025
As of Dec. 1st, 2025 -- Aumannstrasse has now reopened. The Clay Kaserne South Gate is now closed until further notice.
--------
During this work phase, utilize Boyd Blvd. as your main thoroughfare on Clay Kaserne. South Gate will continue to provide an additional egress option, accessible by a detour route off Via Principalis near Newman Village -- from 4-6 p.m., Monday through Friday.
Click on image to enlarge