Feb 2, 2022 - The US Army Engineer Research and Development Center (ERDC) Evaluation Team has assessed the cracks in Towers 1 and 2 parking garage and did not observe any life safety concerns.
A repair contract was awarded on 27 Jan 2022.
Feb 8, 2022 - Construction to repair cracks in the parking structures of Tower 1 and 2 are expected to be completed by 31 March 2022.
March 29, 2022 - Completion date delayed due to cold weather in February. Construction is now expected to be completed by 7 April 2022.
April 7, 2022 - Repair work completed.